Related Post

Capacitor Voltage Transformer or CVTVarly loop test for locating underground cable faultSkin effect of the conductor in Transmission linePower System Mock Test & online MCQ practice paperBusbar SystemDouble Bus and Double Breakers scheme.Main and Transfer Busbar ArrangementSingle Bus bar arrangementSectionalized Single Busbar System Sag calculation in overhead lineMurray loop test for locating underground cable faultUnderground Cable

Index

SymbolsTransformerRelayPower-SystemBasic-electricalACSR-ConductorCircuit-BreakerInterview-questions-of-Basic-ElectricityInterview-questions-of-transformerInsulatorCurrent-TransformerMCQMCQ-powersystemThermal-power-stationInterview-questions-of-Power-SystemPower-ElectronicsInterview-questions-of-Underground-CableInterview-questions-of-IlluminationIlluminationMCQ-of-ElectronicsMCQ-of-Basic-ElectricalMCQ-of-Transformers MCQ-of-D.C-motor MCQ-of-D.C-generatorsMCQ-Control-SystemMCQ-Measurementsmcq-of-Generation-power-systemMCQ-of-Induction-MotorMCQ-of-Transmission-DistributionMCQ-of-Electrical-MachinesMCQ-of-Alternator-and-Synchronous-MotorsMCQ-Electric-Power

Sectionalized Single Busbar System


≪ Previous Next ≫

In this scheme, the main bus is sectionalized by a bus coupler breaker & two nos. isolators by which the main busbar can be done separately as when required. The shutdown of one portion of the busbar can be taken for any maintenance work purpose. It is shown in the below fig.



The advantage & disadvantage of sectionalized single bus system is given below:-

Advantage:

  1. The operation of this system is a simple as that of the single busbar system.
  2. Maintenance cost is low.
  3. For maintenance or repairing of the busbar, only one-half of the busbar is required to be de-energized, hence the possibility of a complete shutdown is thereby avoided.
  4. It is possible to utilize the busbar potential for the line relays.

Disadvantage:

  1. The main disadvantage, when a circuit breaker of any circuit of this system fails, power can not be given the said circuit until rectification of the circuit breaker.
  2. For regular maintenance work at busbar, one of half busbar is required to be de-energized, hence feeders & transformer of that portion will be kept in off condition.
  3. If at any stage, a circuit is required to be added to the existing system, half of the busbar is to be de-energized during the period the work is carried out.


≪ Previous Next ≫


Related topics :


Recent Post

Multiple Choice Question (MCQ) of Transmission and Distribution page-3:
21. ACSR conductor implies
A) Anodized Core Smooth Run
B) Anode current sinusoidally run
C) Aluminium conductor steel reinforced
D) All conductors surface treated and realigned.

Read more...

Multiple Choice Question (MCQ) of Transmission and Distribution page-2:
11. In overhead transmission lines the effect of capacitance can be neglected when the length of line is less than
A) 80 km
B) 100 km
C) 160 km
D) 200 km.

Read more...

Multiple Choice Question (MCQ) of Transmission and Distribution page-1:
1. Which of the following is not the transmission voltage in India ?
A) 400 kV
B) 264 kV
C) 132 kV
D) 66 kV.

Read more...